The expansion and renovation of Conestoga High School in Tredyfrin/Easttown School District provides a comprehensive 21st Century educational environment for current and future students.

Project planning balanced existing conditions, utilities, and site constraints and a complicated sloping topography with opportunities for enhanced instructional space. Most importantly, the design responded to the need for Conestoga High School to remain open and operational during construction.

The addition design centers around a translucent roofed atrium that plays off the silhouette of a Conestoga Wagon. The day-lit atrium provides breakout spaces for collaborative small group instruction and study areas and leads to STEAM classrooms beyond. Art classrooms deliberately open onto the atrium to enhance instructional space and serve as a display gallery. The Fabrication Laboratory provides an innovative and collaborative space for students working in art, science, engineering, and math.

The new atrium moves the students from the existing school into the classroom addition. Existing building renovations provide cafeteria expansion for student population growth, additional core classroom space, upgraded science labs, expansion of fitness facility, additional FCS instructional classroom, expansion of the library, expanded and upgraded Nurse’s suite, additional restrooms, and expansion of the student services.

Architect

Heckendorn Shiles Architects

347 East Conestoga Rd.
Wayne, PA 19087
hsarch.com
Matthew Heckendorn, AIA, LEED AP, NCARB, Principal
610-994-3500

Design Team

  • David Farabaugh, Heckendorn Shiles Architects, Project Manager
  • TJ Barszczewski, Project Architect
  • Ariel Ricciuti, Project Interior Designer
  • Craig Bryson, Pennoni
  • Paul Wiedorn, A.W. Lookup Corp.
  • Rich Delp, Schiller and Hersh Associates

Owner/Client

Tredyffrin/Easttown School District
Wayne, PA
Art McDonnell, Business Manager

Key Stats

  • Grades Served: 9–12
  • Capacity of Students/Occupants: 2,400
  • Size of Site: 27 acres
  • Gross Area of Bldg./Space: 381,000 gsf
  • Project Cost: $34,700,000
  • Occupation Date: 9/3/2021

Award Issue

Spring 2025
— Outstanding Project

Photography

©Don Pearse Photographers

Related Projects

2024 Outstanding Project

Outstanding Project

ACCESS Community Center

Heckendorn Shiles Architects