North Riverside, IL

Komarek School

Combined-Level School

Renovation/Addition

Entire Building

2024 Outstanding Project

This post was originally published on this site.

Komarek School District 94 has provided educational needs to the PreK through 8th grades for over 75 years. The existing facility consisted of two structures with a connecting bridge spanning over 13th Avenue. The challenge became how to balance maintenance needs of the facility with curricular needs. A number of community hearings occurred over the course of two years to get feedback and plan for the future. In March 2020, the community voted in approval of a referendum & the overall Master Plan design.

The major goal of the Master Plan was to minimize circulation, create a safe and secure entry, & unify the two buildings into one as best as possible. The new addition to the west building brought all core classrooms under one roof, created a secure pre-school, established one main entrance, and re-zoned all grade levels. Working with the Village, the center street was vacated & turned into a play space that allowed for better supervision and security. On the east end of the site, a majority of the existing building was removed, and a new competitive gymnasium was constructed to easily separate night events from the existing building & remedy parking congestion by pulling it off the street & onto the site.

Architect

ARCON Associates

2050 S. Finley Rd., Ste. 40
Lombard, IL 60148
arconassoc.com
George D. Demarakis, Principal
630-495-1900

Photography: @2024 Kasia Vetter Photography; @2023 Juan Palomo

Photography: @2024 Kasia Vetter Photography; @2023 Juan Palomo

Photography: @2024 Kasia Vetter Photography; @2023 Juan Palomo

Design Team

  • Nicholas & Associates, Inc., Construction Manager
  • 20/10 Engineering Group, Structural Engineer
  • CS2 Design Group, Mechanical/Electrical Engineer

Owner/Client

Komarek School District 94
North Riverside, IL
Dr. Todd Fitzgerald, Superintendent

Key Stats

  • Grades Served: PreK–8
  • Capacity of Students/Occupants: 505
  • Size of Site: 2.17 acres
  • Gross Area of Bldg./Space: 105,966 gsf
  • Space per Student: 209 sq. ft.
  • Cost per Student: $39,275
  • Square Foot Cost: $187
  • Project Cost: $19,834,000
  • Occupation Date: 9/1/2023

Award Issue

Fall 2024
— Outstanding Project

Photography

@2024 Kasia Vetter Photography; @2023 Juan Palomo

Related Projects

2026 Outstanding Project

Outstanding Project

Shepard Middle School

ARCON Associates