Turbotville, PA

Warrior Run Elementary School

Early Childhood School / Elementary School

New Construction

Entire Building

2024 Outstanding Project

For eight years, the Warrior Run School District worked to realize their vision for a new elementary school located on the District’s main campus. The new Warrior Run Elementary School embraces its location and site to provide a learning environment for students to thrive in and to serve the community for generations to come.

A theme of the new school is to put “learning on display”. At its core, is a 2-story skylit Lobby around which the public, shared-use, and related arts spaces are located providing abundant natural light and fostering a sense of community. Overlooking the Lobby is a Learning Stair and small group areas for student collaboration. All classrooms feature windows to the corridor and the Art and STEM rooms boast folding glass walls that allow them to open up to a shared work area for flexible learning opportunities.

To meet the District’s goals for site development, the selected location for the new school included a 45′ elevation change across the site. The resulting design embraces this with a 3-story school that steps with the slope and provides direct site access from all three floors, including a bridge to an outdoor learning plaza from the 3rd floor.

Architect

Breslin Architects

1226 Union Blvd.
Allentown, PA 18109
Breslinarchitects.com
Michael R. Bell, AIA, LEED AP BD+C, Principal
610-437-9626

Design Team

  • Michael R. Bell, AIA, LEED AP BD+C, Principal-In-Charge
  • Michael K. Ackerman, AIA, Senior Design Architect
  • Kevin M. Miller, LEED AP BD+C, Project Manager
  • Chloe R. Fritz, Interior Designer

Owner/Client

Warrior Run School District
Turbotville, PA
Dr. Thor Edmiston, Superintendent

Key Stats

  • Grades Served: K–6
  • Capacity of Students/Occupants: 870
  • Size of Site: 114 acres
  • Gross Area of Bldg./Space: 99,900 gsf
  • Space per Student: 115 sq. ft.
  • Cost per Student: $40,230
  • Square Foot Cost: $350
  • Project Cost: $35,000,000
  • Occupation Date: 3/8/2023

Award Issue

Spring 2024
— Outstanding Project

Photography

@2023 Matt Wargo

Related Projects

2026 Outstanding Project

Outstanding Project

Gockley Elementary School

Breslin Architects
2024 Outstanding Project

Outstanding Project

Sandy Run Middle School

Breslin Architects