• Spring 2027 CFE
  • Acoustic Solution

Easton, MA

Blanche A. Ames Elementary School

Early Childhood School / Elementary School

New Construction

Entire Building

2024 Grand Prize - Over 100,000 sq ft

This post was originally published on this site.

The Town of Easton needed to consolidate three neighborhood elementary schools into a single building for 880 learners while maintaining a welcoming, age-appropriate environment. The school is divided into themed classroom “neighborhoods” based on Easton’s history, marked by distinct colors, interactive elements, and playful benches. The design team used canopies, low stone walls, and connections to the outdoors with warm natural materials to reflect the town’s agricultural heritage and reduce the overall scale.

The design supports inclusivity, creativity, and resilience through universal design principles and playful learning. A central full-story ramp pays tribute to Blanche Ames, the school’s namesake and local figure, with interactive infographics celebrating her achievements in art, writing, and women’s suffrage. A sensory courtyard includes rainwater collection via rain chains, a community garden, and a teaching kitchen for students to grow and prepare vegetables.

Pre-occupancy daylight studies informed the school’s optimal north/south orientation, with solar shades controlling glare and heat gain on south-facing elevations. Each classroom wing is sub-metered to monitor energy usage, encouraging friendly competition to reduce consumption. The project maintained LEED and well Building Standard® and exemplified holistic, sustainable design and educational innovation.

Architect

Perkins Eastman

20 Ashburton Place, Floor 8
Boston, MA 02108
perkinseastman.com
Robert Bell, AIA, Principal
617-712-2115

Design Team

  • Robert Bell, AIA, Principal-in-Charge/Educational Planner
  • Daniel Colli, AIA, Project Manager
  • Dawn Guarriello, AIA, Project Architect
  • Peter Romains, RA, BIM Lead

Owner/Client

Town of Easton
Easton, MA
Lisha Cabral, Superintendent

Key Stats

  • Grades Served: PreK–2
  • Capacity of Students/Occupants: 880
  • Size of Site: 6.5 acres
  • Gross Area of Bldg./Space: 148,422 gsf
  • Space per Student: 169 sq. ft.
  • Cost per Student: $84,000
  • Square Foot Cost: $500
  • Project Cost: $74,000,000
  • Occupation Date: 1/2/2023

Award Issue

Fall 2024

Grand Prize - Over 100,000 Sq. Ft.

Photography

©Andrew Rugge, ©Perkins Eastman

Related Projects

2026 Honor Award

Honor Award

Tobin Montessori and Darby Vassall Upper Schools Complex

Perkins Eastman
2025 Citation of Excellence Award

Citation of Excellence Award

Alexandria City High School: Minnie Howard Campus

Perkins Eastman
2024 Grand Prize

Grand Prize

Bard High School Early College

Perkins Eastman DC